The 2020 fieldwork was organised and carried out without disruption of the volume and without accidents. The anti-covid measures were successful. All visitors to the site were quarantined for 2 weeks and no one got sick on the site. The epidemic was controlled within our company. Entry was carried out through the technological road, 3794.6 lm of trenches were traversed with heavy machinery, cleared manually, tested and documented. 104.7 lkm of geological routes were traversed.
The final, third stage of drilling started in September. 3323 lm. All works are in accordance with the approved programme, with the whole complex of related works.
All selected samples were removed from the site and transported to St. Petersburg for sample preparation and subsequent transfer to the laboratory. Gradually the results obtained show excellent convergence with the field XRF measurements.
The company also carried out two audits by State Commission on Reserves experts. A preliminary geological report with reserves calculation and a preliminary technological report. The experts familiarised themselves with all materials and issued two positive expert opinions for the preparation of the final report.
All physical volumes of geological exploration works were completed on time and to the last centimetre. A friendly and efficient team of mechanisers, drivers, mine workers, geologists, supply staff was formed during the field work.
On the photo are exploration ditches, work and machinery on the site. Core storage.